Pasig River Expressway (PAREX)

Project Brief
Project Description

The Pasig River Expressway Project is a 19.37 km six-lane, all elevated expressway which traverses the entirety of Pasig River. The project starts from Radial Road 10 in the City of Manila and shall terminate at a connection to the South East Metro Manila Expressway (C6). The Project will connect and utilize a 2.7-km portion of Skyway Stage 3 from Plaza Azul to San Juan River.

The entire alignment of the project is divided into three segments- (1) Radial Road 10 to MMSS3-Plaza Azul; (Common Alignment with MMSS3) at Plaza Azul to San Juan River; (2) San Juan River (MMSS3 to C5 Intersection; (3) C5 Intersection to C6 Intersection.

Implementing Agency

Toll Regulatory Board

Contractual Arrangement

Supplemental Toll Operation Agreement (STOA)

Region

  • National Capital Region

Sector

Roads

Estimated Project Cost During Approval

Php 95.413 Billion

Procurement Mode

TBD

Contract Term

30 years

Implementation Mode

National

Project Proponent

Pasig River Expressway Corporation - Investor
Skyway O&M Corporation - Operator

Status

Pre-construction

On 14 March 2022, the Office of the President approved the Supplemental Toll Operation Agreement (STOA) for the Pasig Expressway (PAREX) Project, subject to some conditions.

During the 16 February 2023 TRB Board Meeting, the Board approved the consulting firms shortlisted by PAREX's Corp.
Status as of July 25, 2023: On-going preparation of Detailed Engineering Design (DED)