Implementing Agency
Department of Public Works and Highways (DPWH)
Project Description
The project involves the construction and operation and maintenance (O&M) of an 8 km. 4-lane elevated expressway over the Philippine National Railway (PNR) right of way. It starts from C3 Road in Caloocan through Manila crossing Espana towards PUP, Sta. Mesa connecting Metro Manila Skyway Stage 3 (MMSS3). Once completed, the NLEX-SLEX Connector road is expected to decongest traffic in Metro Manila by providing an alternative to C-5 Road, Efipanio de los Santos Avenue (EDSA), and other major thoroughfares, and cut the travel time between NLEX and SLEX to 15-20 minutes which today takes more than an hour.
Project Cost
PhP 23.20 Billion
Procurement Mode
Unsolicited
PPP Structure
Build-Operate-Transfer (BOT)
Cooperation Period
37 Years (2020 - 2057)
Region
Sector
Road
Private Proponent
Manila North Tollways Corporation
Status
Ground Breaking for Section 2 was held last December 14, 2021. Pre-construction activities by the Contractor are ongoing.
Construction works update: 66.79% overall completion as of November 25, 2022.
• 86.42% complete for Section 1 of the Caloocan and Manila Area only.
• 24.29% complete for Section 2 Manila Area.