The project is a 4-lane, 7.75 km elevated expressway and 2.22 km at-grade feeder road that will provide access to NAIA Terminals I, II, and III and link the Skyway and the Manila-Cavite Toll Expressway. It starts at the existing Skyway then follows the existing road alignments over Sales Avenue, Andrews Avenue, Domestic Road, and NAIA Road, and has entry/exit ramps at Roxas Boulevard, Macapagal Boulevard, and PAGCOR City. The project involves: a) construction of Phase II; b) construction of at-grade feeder roads leading to/from PAGCOR Entertainment City; and c) operation and maintenance of the expressway.
PHP 17.93 Billion * *Original project cost approved by the NEDA Board on May 30, 2012 was PhP 15.86 billion; the cost increased to PhP 17.93 billion due to the Variation Order amounting to PhP 2.07 billion.
Procurement Mode
Solicited
Contract Term
30 years including construction
Implementation Mode
National
Private Proponent
Vertex Tollways Development Inc. (VTDI)
Status
Phase 2A and Phase 2B operation commenced on September 22, 2016 and December 20, 2016, respectively. 100% compliant with KPIs as of October 2020.
List of Bidders
Prospective Bidders
1. ACI Consortium (Ayala)
2. IL & FS Transportation Network
3. Manila North Tollways Corp.
4. Optimal Infrastructure Development Corporation (SMC)
Prequalified Bidder/s
1. ACI Consortium (Ayala)
2. IL & FS Transportation Network
3. Manila North Tollways Corp.
4. Optimal Infrastructure Development Corporation (SMC)
Bidders
1. Manila North Tollways Corp.
2. Optimal Infrastructure Development Corporation (SMC)
Winning Bidder/s
Optimal Infrastructure Development Corporation (SMC)
Contact Persons
MS. MARIA CATALINA E. CABRAL
Undersecretary, DPWH
(+632) 5304.3268
MR. CARLOS FUNDADOR T. JAYOMA
Project Monitoring Officer, PPP Center
(+632) 8709.4146 local 5209