Republic of the Philippines

Public-Private Partnership Center

MRT Line 7

Project Brief
Implementing Agency

Department of Transportation (DOTr)

Project Description

The project involves the financing, design, construction, operation & maintenance of the 23-kilometer elevated railway line with 14 stations from San Jose Del Monte, Bulacan to MRT 3 North Avenue in Quezon City and the 22-kilometer asphalt road from Bocaue Interchange of the North Luzon Expressway (NLEX) to the intermodal terminal in Tala. The road component will divert northern provincial buses operation to San Jose Del Monte, thereby decongesting EDSA.

 

 

Project Cost

PHP 62.7 Billion

PPP Structure

Build-Gradual Transfer-Operate and Maintain (BGTOM)

Region

  • REGION III - CENTRAL LUZON
  • NATIONAL CAPITAL REGION

Sector

Transportation,Rail

Private Proponent

SMC Mass Rail Transit 7, Inc

Status

51.84% complete as of March 31, 2020. Civil Works is 47.07% complete; and Rolling Stock and Electrical & Mechanical Works is 55.30% complete.

Ongoing construction activities are suspended due to enhanced community quarantine.

  • USEC. TIMOTHY JOHN R. BATAN
    Undersecretary for Rail, Department of Transportation