The project involved the engineering, supply, installation, and construction, testing and commissioning of full turnkey basis of a 300 MW combined Cycle Power Plant.
National Power Corporation (NPC)
Build-Transfer-Operate (BTO)
Power
Php 14.90 Billion (USD 298.00 Million)
Solicited
15 Years (1993-2008)
National
ABB Power Generation LTD., Switzerland
Concluded