Implementing Agency
Leyte Metropolitan Water District (LMWD)
Project Description
The general objective of the project is primarily to attain the highest possible level of water supply service for, as far as feasibly possible, 100% of water consumers within the coverage of the joint venture area. The joint venture area is the service area of Leyte Metropolitan Water District which includes the geographic jurisdiction of the Municipalities of Dagami, Tanauan, Tolosa, Palo, Tabon-Tabon, Santa Fe, Pastrana and City of Tacloban, and future expansion areas.
Estimated Project Cost During Approval
Php 6,143.74 Million
Procurement Mode
Unsolicited
Contractual Scheme
Joint Venture (JV) Agreement
Contract Term
25 Years
Implementation Mode
National
Region
- REGION VIII - EASTERN VISAYAS
Sector
Environmental,Water and Sanitation
Private Propoent
Primewater Infrastructure Corp.
Status
Operational