Project Description

The Project involves the construction of a new 82,600 m2 Passenger Terminal Building (PTB) of the CIA, with a design capacity of 8 million passengers per annum (MPPA).

The Engineering, Procurement, and Construction Contract was signed on January 29, 2018.

 

Project Cost

PhP 12.55 B

Procurement Mode

Solicited (Single-Stage Bidding Process)

PPP Structure

Build-and-Transfer (BT)

Cooperation Period

Not applicable

Region

  • REGION III - CENTRAL LUZON

Sector

Transportation,Airport

Construction Period

December 2017 - 1st Quarter of 2020

Status

Construction on-going; 11.91% complete as of June 30, 2018

BCDA Website:

www.bcda.gov.ph

List of Bidders

Winning Bidder(s)

Megawide Construction Corp. and GMR Infrastructure Ltd.

Timeline

Target Bid Submission Date : December 5, 2017

Issuance of Notice of Award:  December 18, 2017