Implementing Agency
National Power Corporation (NPC)
Project Description
The project involved the design, supply, installation/erection, delivery to mooring site, testing, commissioning and operation of a Power Barge.
Estimated Project Cost During Approval
Php 3.90 Billion (USD 78.00 Million)
Procurement Mode
Solicited
Contractual Scheme
Build-Own-Operate (BOO)
Contract Term
5 Years (1994 - 1999)
Implementation Mode
National
Region
Sector
Power
Private Proponent
Far East Levingston Shipbuilding Ltd.
Status
Concluded