Projects | Release of Advertisement | Period from Issuance of ITPB to Construction Start Date | Project Status as of September 2013 |
---|---|---|---|
Daang Hari-SLEX Link Road | July 20, 2011 | 18 months | Awarded; under construction |
PPP for School Infrastructure Project Phase 1 | January 8, 2012 | 14 months | Awarded; under construction |
NAIA Expressway Phase 2 | July 2012 | 14 months | Awarded; Detailed Engineering Design (DED) being drafted |
Modernization of the Philippine Orthopedic Center (MPOC) Project | November 18, 2012 | 8 months * | Submitted bid for ICC approval |
PPP for School Infrastructure Project Phase 2 | December 21, 2012 | 9 months * | Submitted bids under evaluation |
Automatic Fare Collection System (AFCS) | December 17, 2012 | 9 months * | For bid submission |
MCIA Passenger Terminal Building | December 21, 2012 | 9 months * | For bid submission |
Cavite-Laguna Expressway | April 9, 2013 (Re-advertisement: July 22, 2013) | 5 months * | For prequalification of bidders |
LRT 1 Cavite Extension and O & M | June 4, 2012 | 14.5 months * | For re-bidding |
Rehabilitation and O&M of AHEPP Turbines 4 & 5 | December12, 2012 | n/a | For re-issuance of ITPB |
* From release of Invitation to Prequalify and Bid (ITPB) to current project status