Projects Release of Advertisement Period from Issuance of ITPB to Construction Start Date Project Status as of September 2013
Daang Hari-SLEX Link Road  July 20, 2011 18 months Awarded; under construction
PPP for School Infrastructure Project  Phase 1 January 8, 2012 14 months Awarded; under construction
NAIA Expressway Phase 2  July 2012 14 months Awarded; Detailed Engineering Design (DED) being drafted
Modernization of the Philippine Orthopedic Center (MPOC) Project November 18, 2012 8 months * Submitted bid for ICC approval
PPP for School Infrastructure Project Phase 2 December 21, 2012 9 months * Submitted bids under evaluation
Automatic Fare Collection System (AFCS)  December 17, 2012 9 months * For bid submission
MCIA Passenger Terminal Building December 21, 2012 9 months * For bid submission
Cavite-Laguna Expressway April 9, 2013 (Re-advertisement: July 22, 2013) 5 months * For prequalification of bidders
LRT 1 Cavite Extension and O & M June 4, 2012 14.5 months * For re-bidding
Rehabilitation and O&M of AHEPP Turbines 4 & 5 December12, 2012 n/a For re-issuance of ITPB

* From release of Invitation to Prequalify and Bid (ITPB) to current project status