PPP Project Update: Clark International Airport Expansion Project

As of March 2019, the Clark International Airport Expansion Project is 52% complete. This was announced by Bases Conversion and Development Authority (BCDA) President Vince Dizon during the site inspection conducted on March 27, 2019. The project involves the construction of a new 93,000 sq. m. Passenger Terminal Building, with a design capacity of 8 million passengers per annum. The construction is expected to be completed by mid-2020.​