Implementing Agency
City Government of Tuguegarao
Project Description
The Project involves the financing, design, construction, development, and operation of Tuguegarao City’s septage management system with the following components:
- Finance, design, construction, operation, and maintenance of septage treatment plant with a capacity of 80 cubic meters per day
- Conduct of Census, Collection, Transport, Treatment of Sludge and Septage and proper disposal or re-use of Biosolids treated effluent and residual bio-solids
Estimated Project Cost During Approval
Php 110.49 Million
Procurement Mode
Unsolicited
Contractual Scheme
Joint Venture (JV) Agreement
Contract Term
25 years
Implementation Mode
Local
Region
- REGION II - CAGAYAN VALLEY
Sector
Environmental,Water and Sanitation
Private Proponent
Envirokonsult Equipment and Services, Inc.
Status
Notice of Award was issued on January 11, 2022.