The project involves the 21.65-km extension of the NLEX from Mindanao Avenue, Quezon City to the C-3 (Circumferential Road 3) in Caloocan City and to Commonwealth Avenue in Quezon City.
Php 26.020 Billion
Unsolicited
Supplemental Toll Operation Agreement
-
Road
Manila North Tollways Corporation (MNTC)
Operational
SEGMENT 8.1 Completed and opened to the public on June 2010.
SEGMENT 8.2 - Detailed Engineering Design (DED) approved by TRB. - Ongoing Right-of-Way Acquisition by the DPWH SEGMENT 9 Completed and opened to the public on March 19, 2015.
SEGMENT 10 - Right-of-Way Acquisition by the DPWH is 100.00% delivered - Inaugurated on February 28, 2019 and opened to traffic on March 01, 2019 - Ongoing completion of remaining works/punch list items SEGMENT 10, EXIT RAMP TO R-10 - Ongoing construction, 72% accomplishment - Right-of-Way Acquisition is 94% completed - ISF Relocation is 91.21% completed
Source: DPWH briefer and website