Implementing Agency
Department of Transportation (DOTr)
Project Description
The project involves the construction and operation & maintenance of a new modern airport in Bulacan with a design capacity of 200 million passengers per year, consisting of 4 runways and all aviation related facilities
Indicative Cost
PhP 735.60 Billion
Procurement Mode
Unsolicited
PPP Structure
Build-Operate-Transfer (BOT)
Cooperation Period
50 years (2027-2077)
Region
- REGION III - CENTRAL LUZON
Sector
Transportation,Airport
Private Proponent
San Miguel Aerocity Inc.
Status
Ongoing pre-construction activities as of December 30, 2022:
- Land Development works progress:
- Site clearance - 94.06% complete;
- Land filling - 52.81% complete;
- Preparation of Detailed Engineering Design
- Right-of-Way (ROW) acquisition - 97.66% complete
- Procurement of Independent Certification Engineer