Implementing Agency
Department of Transportation (DOTr)
Project Description
The project involves the construction, operation and maintenance of a new modern airport in Bulacan with a design capacity of up to 100 million passengers per year, consisting of 4 runways and all aviation related facilities.
Estimated Project Cost During Approval
PhP 735.63 Billion
Procurement Mode
Unsolicited
Contractual Scheme
Build-Operate-Transfer (BOT)
Contract Term
50 years
Implementation Mode
National
Region
- REGION III - CENTRAL LUZON
Sector
Transportation,Airport
Private Proponent
San Miguel Aerocity Inc.
Status
Ongoing pre-construction activities as of January 31, 2024:
- Land Development works ongoing: (Total Progress: 77.63%)
- Site clearance: 100.00%
- Land filling: 78.31%
- Ground Improvement works: 92.52%
- Preparation of Detailed Engineering Design
- Right-of-Way (ROW) acquisition: 98.42%