New Manila International Airport (Bulacan International Airport)

Project Brief
Project Description

The project involves the construction, operation and maintenance of a new modern airport in Bulacan with a design capacity of up to 100 million passengers per year, consisting of 4 runways and all aviation related facilities.

Implementing Agency

Department of Transportation (DOTr)

Contractual Arrangement

Build-Operate-Transfer (BOT)

Region

  • Region III - Central Luzon

Sector

Transportation,Airport

Estimated Project Cost During Approval

PhP 735.63 Billion

Procurement Mode

Unsolicited

Contract Term

50 years

Project Type

National

Private Proponent

San Miguel Aerocity Inc.

Status

Ongoing pre-construction activities as of July 31, 2024:

  • Land Development works ongoing: (Total Progress: 84.61%)
    • Site clearance: 100.00%
    • Land filling: 77.49%
    • Ground Improvement works: 94.27%
    • Right-of-Way (ROW) for Airport Site: 99.47%
    • ROW for Airport Toll Road: 29.35%