Project Description
The project involves the construction, operation and maintenance of a new modern airport in Bulacan with a design capacity of up to 100 million passengers per year, consisting of 4 runways and all aviation related facilities.
Implementing Agency
Department of Transportation (DOTr)
Contractual Arrangement
Build-Operate-Transfer (BOT)
Region
- Region III - Central Luzon
Sector
Transportation,Airport
Estimated Project Cost During Approval
PhP 735.63 Billion
Procurement Mode
Unsolicited
Contract Term
50 years
Project Type
National
Private Proponent
San Miguel Aerocity Inc.
Status
Ongoing pre-construction activities as of July 31, 2024:
- Land Development works ongoing: (Total Progress: 84.61%)
- Site clearance: 100.00%
- Land filling: 77.49%
- Ground Improvement works: 94.27%
- Right-of-Way (ROW) for Airport Site: 99.47%