New Manila International Airport (Bulacan International Airport)

Project Brief
Implementing Agency

Department of Transportation (DOTr)

Project Description

The project involves the construction and operation & maintenance of a new modern airport in Bulacan with a design capacity of 200 million passengers per year, consisting of 4 runways and all aviation related facilities

Indicative Cost

PhP 735.60 Billion

Procurement Mode

Unsolicited

PPP Structure

Build-Operate-Transfer (BOT)

Cooperation Period

50 years (2027-2077)

Region

  • REGION III - CENTRAL LUZON

Sector

Transportation,Airport

Private Proponent

San Miguel Aerocity Inc.

Status

Ongoing pre-construction activities as of December 30, 2022:

  1. Land Development works progress:
    • Site clearance - 94.06% complete;
    • Land filling - 52.81% complete;
  2. Preparation of Detailed Engineering Design
  3. Right-of-Way (ROW) acquisition - 97.66% complete
  4. Procurement of Independent Certification Engineer

  • ENGR. ELHAINE MAE L. SABINO