New Manila International Airport (Bulacan International Airport)

Project Brief
Implementing Agency

Department of Transportation (DOTr)

Project Description

The project involves the construction, operation and maintenance of a new modern airport in Bulacan with a design capacity of up to 100 million passengers per year, consisting of 4 runways and all aviation related facilities.

Estimated Project Cost During Approval

PhP 735.63 Billion

Procurement Mode

Unsolicited

Contractual Scheme

Build-Operate-Transfer (BOT)

Contract Term

50 years

Implementation Mode

National

Region

  • REGION III - CENTRAL LUZON

Sector

Transportation,Airport

Private Proponent

San Miguel Aerocity Inc.

Status

Ongoing pre-construction activities as of January 31, 2024:

  • Land Development works ongoing: (Total Progress: 77.63%)
    • Site clearance: 100.00%
    • Land filling: 78.31%
    • Ground Improvement works: 92.52%
  • Preparation of Detailed Engineering Design
  • Right-of-Way (ROW) acquisition: 98.42%