New Manila International Airport (Bulacan International Airport)

Project Brief
Implementing Agency

Department of Transportation (DOTr)

Project Description

The project involves the construction and operation & maintenance of a new modern airport in Bulacan with a design capacity of 200 million passengers per year, consisting of 4 runways and all aviation related facilities

Indicative Cost

PhP 735.634 Billion

Procurement Mode

Unsolicited

Contractual Scheme

Build-Operate-Transfer (BOT)

Contract Term

50 years

Implementation Mode

National

Region

  • REGION III - CENTRAL LUZON

Sector

Transportation,Airport

Private Proponent

San Miguel Aerocity Inc.

Status

Ongoing pre-construction activities as of July 31, 2023:

  1. Land Development works progress: (Total Progress: 66.12%)
    • Site clearance - 97.38% complete;
    • Sand Supply - 76.54% ;
    • PVD Installation - 64.53%
    • Surcharge Removal - 22.48%
  2. Preparation of Detailed Engineering Design
  3. Procurement of Independent Certification Engineer
  4. Right-of-Way (ROW) acquisition - 98.08% complete

  • ENGR. ELHAINE MAE L. SABINO
    Project Monitoring Officer, PPP Center
    (+632) 8709.4146 local 5208