Republic of the Philippines

Public-Private Partnership Center

Mindanao Diesel Power Barges Project

Project Brief
Implementing Agency

National Power Corporation (NPC)

Project Description

The project involved the design, manufacture, supply, delivery to site, construction, installation/erection testing and commissioning in full turnkey and the second operation and maintenance of two (2) x 100 MW Power Barges for the purpose of converting fuel delivered by NPC into electricity.

Estimated Project Cost During Approval

PhP 16.75 Billion

Procurement Mode

Solicited

Contractual Scheme

Build-Transfer-and-Operate (BTO)

Contract Term

15 Years (1994-2009)

Implementation Mode

National

Region

  • REGION XI - DAVAO
  • REGION XIII - CARAGA

Sector

Power

Private Proponent

MITSUI Engineering & Shipbuilding, Ltd. (MES); Burmeister & Wain Scandinavian Contractor (BWSC)
Consortium of Mitsui & Company Limited (Japan / Denmark)

Status

Concluded