Republic of the Philippines

Public-Private Partnership Center

Metro Manila Expressway C6

Project Brief
Implementing Agency

Philippine National Construction Corporation (PNCC) and Toll Regulatory Board

Project Description

The project involves the design, construction, financing, operation and maintenance of the toll road, consisting the Southeast Metro Manila Expressway, the East Metro Manila Expressway, and the Northeast Metro Manila Expressway.

Project Cost

Php 35.5 Billion

Procurement Mode

Solicited

PPP Structure

Supplemental Toll Operation Agreement

Cooperation Period

30 years

Region

  • NATIONAL CAPITAL REGION

Sector

Road

Private Proponent

Citra Intercity Tollways Incorporated (CITI)

Status

Under construction.

Ongoing activities for SEMME Phase 1:
- Right of way acquisition for Section 1B.
- Civil works, Section 1: Construction on workable area at C5 (Piers 61 to 66), 100% accomplishment
- Awaiting delivery of available ROW and finalization of revised DED drawings for Section 1A (interfacing SEMME with NSCR and MMSP) and Section 2 realignment to continue construction activities .
-Ongoing tree-cutting along the highway (based on IC report)

Source: DPWH briefer as of July 25, 2022

  • MS. WYNONA MARIE R. SILVERIO
    Project Monitoring Officer, PPP Center
    (+632) 8709.4146 local 5206