The current LRT Line 1 will be extended starting from its existing Baclaran Station to the future Niyog Station in Bacoor, Cavite which is approximately 11.7 kilometers. Of this length, 10.5 kilometers will be elevated and 1.2 kilometers will be at-grade. The whole stretch of the integrated LRT 1 will have a total length of approximately 32.4 kilometers and will be operated and maintained by the private proponent.
The private partner will undertake the design, construction, and financing of the Cavite Extension as well as the operation and maintenance of the integrated system upon completion of the project. The concessionaire will also undertake future system maintenance and upgrades as well as permitted commercial development.
Project Cost
PHP 64.915 Billion
Procurement Mode
Solicited
PPP Structure
Build-Transfer-and-Operate (BTO)
Cooperation Period
32 years
Implemention Mode
National
Region
REGION IV-A - CALABARZON
NATIONAL CAPITAL REGION
Sector
Rail,Transportation
Private Proponent
Light Rail Manila Corporation
Status
Under construction
EPCC Combined Works 85.67% complete as of February 28, 2023. - Existing System Works 99.93% complete; - Cavite Extension Phase 1 Works 80.92% complete