Manila-Cavite Toll Expressway (including C5 South Link Expressway Project)

Project Brief
Implementing Agency

Toll Regulatory Board (TRB) and Philippine Reclamation Authority (PRA)

Project Description

The project involves the construction of the following segments:

  • R-1 Expressway, which involves the upgrading of a 6.6 km two-lane dual carriageway to a three-lane dual expressway standard in a highly populated coastal area;
  • The C-5 Link Expressway, consisting of the construction of a 6.0 km, three-lane dual carriageway in a highly populated urban area; and
  • The R-1 Expressway Extension, which involves the construction of 11.4 kms of two-lane dual carriageway, 5.0 kms of which will be a viaduct.

Estimated Project Cost During Approval

Php 6.55 Billion

Procurement Mode

Unsolicited

Contractual Scheme

Toll Operation Agreement

Contract Term

35 Years

Implementation Mode

National

Region

  • NATIONAL CAPITAL REGION
  • REGION IV-A - CALABARZON

Sector

Roads

Private Proponent

Cavitex Infrastructure Corporation (CIC); Public Estates Authority; UEM - MARA Philippines Corporation/Coastal Road Corporation

Status

R-1 Expressway: Segment 1 - Operational

C-5 Link Expressway
Segment 2 - ongoing construction.
Ongoing construction is 32.86% complete, as of March 2023.
Ongoing ROW Acquisition by DPWH is at 86.88% complete, as of March 2023.

Segment 3 - ongoing construction
Segment 3A-1: Inaugurated and opened to traffic on July 23, 2019.
Segment 3A-2: Opened to traffic on August 14, 2022.
Segment 3B: Ongoing ROW Acquisition by DPWH at 67.33%, as of March 2023. DED Drawings approved by TRB.

R-1 Expressway Extension
Segment 4 - Pre-construction
Segment 5 - Pre-construction

CIC is set to implement new toll rates starting on May 12, 2022.

Source: C5 South Link Expressway Project Webpage posted by DPWH PPP Service
Cavite Expressway Website