Project Brief
Implementing Agency

National Power Corporation (NPC)

Project Description

The project located in Brgy. Malaya, Pililla, Rizal, involved rehabilitation of the existing power generating units in the power complex, extend the effective life of the equipment thereon, and make the power complex more responsive and effective in dealing with day-to-day operation.

Estimated Project Cost During Approval

Php 12.50 Billion (USD 250.00 Million)

Procurement Mode

Solicited

Contractual Scheme

Rehabilitate-Operate-Maintain and Manage (ROMM)

Contract Term

15 Years (1995-2010)

Implementation Mode

National

Region

  • REGION IV-A - CALABARZON

Sector

Power

Private Proponent

KEPCO, Philippines Corporation – KEPCO Korea Electric Power Corp. (KEPCO)

Status

Concluded