Mactan-Cebu International Airport Passenger Terminal Building

Project Brief

MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2
MCIA Passenger Terminal 2

Implementing Agency

Department of Transportation (DOTr) and Mactan Cebu International Airport Authority

Project Description

The project involves the construction of a new world-class passenger terminal building in MCIA, with a capacity of about 8 million passengers per year; and the operation of the old and new facilities. The construction of a new world-class passenger terminal, including all related facilities, is proposed to separately cater to domestic and international operations.

Project Cost

PhP 17.52 Billion

Procurement Mode

Solicited

PPP Structure

Build-Operate and Transfer (BOT)

Cooperation Period

25 years

Region

  • REGION VII - CENTRAL VISAYAS

Sector

Transportation,Airport

Private Proponent

GMR Infrastructure and Megawide Consortium

Status

Construction 100% complete as of August 31, 2019

Terminal 2 commenced operations on June 30, 2018; Terminal 1 rehabilitation works completed on August 31, 2019

During the enhanced community quarantine implemented in the Cebu Region, only sweeper and cargo flights were allowed to operate until May 15, 2020. Operations for domestic commercial flights at Terminal 1 resumed on June 6, 2020. With the opening of the first dedicated Covid-19 Testing Laboratory at Terminal 2 on July 12, 2020, International Flights restarted its operations on July 15, 2020. Both Terminals are implementing new protocol and routine to ensure passenger health safety.

DOTR Website

http://dotr.gov.ph/

Mactan-Cebu International Airport Website

Mactan-Cebu International Airport

List of Bidders
Prospective Bidders

1. Aboitiz Land Inc.
2. Filinvest Land Inc.
3. GMR Infrastructure Limited
4. JG Summit Holdings, Inc.
5. Macroasia Corporation
6. Megawide
7. Metro Pacific Investments
8. Prime Power Holdings Corporation
9. San Miguel Corporation
10. First Philippine Holdings
11. Premier Airport Group (c/o SM Investments Corporation)

Pre-qualified Bidders

1. AAA Airport Partners
2. Filinvest-CAI Consortium
3. First Philippine Airports
4. GMR Infrastructure and Megawide Consortium
5. MPIC-JGS Airport Consortium
6. SM-led Premier Airport Group
7. San Miguel Incheon-Airport Consortium

Bidders

1. AAA Airport Partners
2. Filinvest-CAI Consortium
3. First Philippine Airports
4. GMR Infrastructure and Megawide Consortium
5. MPIC-JGS Airport Consortium
6. SM-led Premier Airport Group
7. San Miguel Incheon-Airport Consortium

Winning Bidder/s

GMR Infrastructure and Megawide Consortium

  • MS. JEZZEL R. JAO
    Project Monitoring Officer, PPP Center
    (+632) 8709.4146 local 5203