Project Description

The project involved the design, supply, construction, financing, testing and operation of 200 MW power plants which utilize geothermal in the Greater Tongonan area of Leyte, comprising the Upper Mahiao and Malitbog sectors.

Project Cost

Php 2.30 Billion (USD 46.00 Million)

Procurement Mode

Solicited

PPP Structure

Build-Operate-Transfer (BOT)

Cooperation Period

10 years (1997-2007)

Region

  • REGION VIII - EASTERN VISAYAS

Sector

Power

Private Proponent

Ormat, Inc. (USA)

Status