Project Description
The Southwest Terminal of the Integrated Transport System (ITS) project will be constructed within a site area of 4.59 hectares. It will connect passengers coming from the Cavite side to other transport systems such as the future LRT Line 1 South Extension, city bus, taxi, and other public utility vehicles that are serving inner Metro Manila. The project will include passenger terminal buildings, arrival and departure bays, public information systems, ticketing and baggage handling facilities, and park-ride facilities.
The private partner will undertake the design, construction, and financing of the ITS terminal as well as the operation and maintenance of the whole facility. It can also undertake commercial development and collect revenues generated from the same.
Estimated Project Cost During Approval
PHP 2.50 Billion
Procurement Mode
Solicited Mode; Single-Stage Bidding
Contractual Scheme
Build-Transfer-and-Operate (BTO)
Contract Term
35 years inclusive of construction period
Implementation Mode
National
Region
Sector
Transport Terminal,Transportation
Private Proponent
MWM Terminals, a consortium of Megawide Construction Corp. and WM Property Management Inc.
Status
Operational