Clark International Airport Expansion Project – Engineering, Procurement and Construction (EPC)

Project Brief
Implementing Agency

Bases Conversion and Development Authority

Project Description

The Project involves the construction of a new 82,600 m2 Passenger Terminal Building (PTB) of the CIA, with a design capacity of 8 million passengers per annum (MPPA).

The Engineering, Procurement, and Construction Contract was signed on January 29, 2018.

 

Project Cost

PhP 12.55 B

Procurement Mode

Solicited (Single-Stage Bidding Process)

PPP Structure

Build-and-Transfer (BT)

Cooperation Period

Not applicable

Region

  • REGION III - CENTRAL LUZON

Sector

Transportation,Airport

Construction Period

December 2017 - 1st Quarter of 2020

Status

EPC Contract signed on January 29, 2018; Construction on-going; 74.58% complete as of July 31, 2019

BCDA Website:

www.bcda.gov.ph

List of Bidders

Prospective Bidders

  1. Al McDonald Arabia
  2. Atlantic Gulf and Pacific Company of Manila
  3. China Harbour Engineering Corp.
  4. China State Construction Engineering Corp.
  5. DABS Consortium
  6. First Balfour Inc.
  7. GMR-Megawide Consortium
  8. POSCO
  9. Qingjian Group Corp.
  10. RII Builders Inc.
  11. Sinohydro
  12. Tokwing Construction Corp.

Bidders

  1. GMR-Megawide Consortium
  2. Sinohydro
  3. China Harbour Engineering Corp.
  4. China State Construction Engineering Corp.
  5. Tokwing Construction Corp.

Winning Bidder(s)

GMR-Megawide Consortium
Megawide Construction Corporation
GMR Infrastructure (Singapore) Pte. Limited
GMR Holdings Overseas (Singapore) Pte. Limited

Timeline

Target Bid Submission Date : December 5, 2017

Issuance of Notice of Award:  December 18, 2017

 

  • AR. ALI FATIMA BAHOY
    Project Monitoring Officer, PPP Center
    (+632) 709.4146 local 5206