Cavite EPZA Diesel Plant Project

Project Brief
Implementing Agency

National Power Corporation (NPC)

Project Description

The project involved the design, development, financing, construction, completion, testing and commissioning of the Power plant, including the transmission line and switchyard, fuel receiving and storage facilities and other site development works. It also included the supply, installation and testing of the additional substation equipment needed for the interconnection of the Rosario substation.

Project Cost

Php 1.10 Billion (USD 22.00 Million)

Procurement Mode

Solicited

PPP Structure

Build-Operate-Transfer (BOT)

Cooperation Period

10 years (1995-2005)

Region

  • REGION IV-A - CALABARZON

Sector

Power

Private Proponent

Magellan Cogeneration, Inc. (Philippines)

Status

Concluded