Republic of the Philippines

Public-Private Partnership Center

Caliraya-Botocan-Kalayaan (CBK) Power Plant

Project Brief
Implementing Agency

National Power Corporation (NPC)

Project Description

The Operator will finance, design, build, rehabilitate, upgrade, expand, commission, test, operate, maintain and manage the CBK Complex and transfer the same to NPC at the end of the cooperation period.

Estimated Project Cost During Approval

Php 22.50 Billion (USD 450 Million)

Procurement Mode

Unsolicited

Contractual Scheme

Build-Rehabilitate-Operate-Transfer (BROT)

Contract Term

25 years

Implementation Mode

National

Region

  • REGION IV-A - CALABARZON

Sector

Power

Private Proponent(s)

CBK Power Corporation

Status

Operational

  • MR. RONALD M. MANGILIN
    Project Monitoring Officer, PPP Center
    (+632) 8709.4146 local 5205