Republic of the Philippines

Public-Private Partnership Center

Bohol Provincial Electric System Project

Project Brief
Implementing Agency

Provincial Government of Bohol

Project Description

The project involved the financing, rehabilitation, ownership, operation, maintenance and management of the Provincial Electric System.

Estimated Project Cost During Approval

Php 0.25 Billion

Procurement Mode

Solicited

Contractual Scheme

Joint Venture (JV) Agreement

Contract Term

20 Years (2000-2019)

Implementation Mode

Local

Region

  • REGION VII - CENTRAL VISAYAS

Sector

Power

Private Proponent

Bohol Light Company Inc.
Consortium Members: Salcon International, Inc. (SII), Salcon Power Corporation and Pure and Pam, Inc.

Status

Concluded