Bulacan Bulk Water Supply Project

Project Brief

012BBWS_4IMP_20170208_PHO_construction-progress1.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction1.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction2.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction3.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction4.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction5.JPG
BBWS_20190422_PHO_ongoing-construction1.png
BBWS_20190422_PHO_ongoing-construction2.png
BBWS_20190422_PHO_ongoing-construction3.png
BBWS_20190422_PHO_ongoing-construction4.png
BBWS_20190422_PHO_ongoing-construction5.png
BBWS_20190422_PHO_ongoing-construction6.png
view of the Water Treatment Plant Facility as of Feb 8 2017
Deep excavation activities in the Lift Pumping Station as of Feb 8 2017
Soil excavation and slope trimming activities in the Pumping Station as of Feb. 8, 2017
Rebar installation at ground slab and columns and lean concrete pouring activities in the Treated Water Reservoir as of Feb. 8, 2017
Lean concrete pouring and reinforcing bars and formworks installation activities in the Treated Water Reservoir as of Feb 8 2017
Formworks and catwalk installation and concrete pouring activities in the lower ground slab of the Treated Water Reservoir as of Feb 8 2017
Concrete pouring at lower ground wall activities in the Treated Water Reservoir as of Feb 8 2017
012BBWS_4IMP_20170406_PHO_ongoing-construction1.jpg
012BBWS_4IMP_20170406_PHO_ongoing-construction2.jpg
012BBWS_4IMP_20170406_PHO_ongoing-construction3.jpg
012BBWS_4IMP_20170406_PHO_ongoing-construction4.jpg
012BBWS_4IMP_20170406_PHO_ongoing-construction5.jpg
012BBWS_4IMP_20170406_PHO_ongoing-construction6.jpg
012BBWS_4IMP_20170406_PHO_ongoing-construction7.jpg
012BBWS_4IMP_20170406_PHO_ongoing-construction8.jpg
012BBWS_4IMP_20170208_PHO_construction-progress1.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction1.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction2.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction3.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction4.JPG
012BBWS_4IMP_20170526_PHO_ongoing-construction5.JPG
BBWS_20190422_PHO_ongoing-construction1.png
BBWS_20190422_PHO_ongoing-construction2.png
BBWS_20190422_PHO_ongoing-construction3.png
BBWS_20190422_PHO_ongoing-construction4.png
BBWS_20190422_PHO_ongoing-construction5.png
BBWS_20190422_PHO_ongoing-construction6.png

 

Implementing Agency

Metropolitan Waterworks and Sewerage System (MWSS)

Project Description

The project will provide treated bulk water to the various water districts (WDs) of Bulacan to help meet the increasing water demand of its consumers, expand its current service area coverage and increase the households served. The private partner will undertake the financing, detailed design and construction, and maintenance of conveyance facilities, treatment facilities and water source.
The project will include the construction of various components, such as:

a) Water Source/s;
b) Aqueduct Interconnection, Intake and Lift Station for raw water abstraction;
c) Water Treatment Plant complete with support buildings and structures, treated water reservoir, including Sludge Treatment Facility;
d) Raw and Treated Water conveyance facilities complete with necessary appurtenances;
e) Facilities for interconnection with the WDs;
f) Bridge, Culvert, and River Crossings;
g) SCADA system;
h) Booster Pump Stations;
i) Security Perimeter Fencing;
j) Inventory of Materials and Vehicles; and
k) Access Road and Pipe Bridge Support.

Estimated Project Cost During Approval

PhP 24.41 Billion

Procurement Mode

Solicited

Contractual Scheme

Build-Operate-and-Transfer (BOT)

Contract Term

30 years (inclusive of construction)

Implementation Mode

National

Region

  • REGION III - CENTRAL LUZON

Sector

Water & Sanitation

Project Proponent

Luzon Clean Water Development Corporation (LCWDC)
Consortium Members: San Miguel Holdings Inc. and Korea Water Resources Corporation

Status

Ongoing operations of Stage 1 and Stage 2 since January 24, 2019 and April 25, 2019 respectively.

Compliance to Key Performance Indicators for December 2023:

  • KPI 1 - Availability of Supply: 114.88% Compliance (supply of treated bulk water is above the required contracted volume)
  • KPI 2 – Water Quality: 100% Compliance
  • KPI 3 – Pressure: 100% Compliance
  • KPI 4 – Service Coverage: 100% Compliance
  • KPI 5 – Non-Revenue Water (NRW): 100% Compliance (allowable NRW is up to 5%; for December 2023, 3.70% NRW was recorded).

List of Bidders

Prospective Bidders

1. Manila Water (Philippines)
2. Marubeni (Japan)
3. Filinvest (Philippines)
4. First Balfour (Philippines)
5. Abengoa (Spain)
6. Megawide (Philippines)
7. San Miguel (Philippines)
8. Maynilad Water Services, Inc.(Philippines)
9. New San Jose Builders, Inc. (Philippines)
10. Sojitz Corp.(Japan)
11. Korea Water Resources Corp.(Korea)
12. Prime Water Infrastructure Corp (Philippines)
13. Datem Water, Inc. (Philippines)
14. Acciona Agua (Spain)
15. Aboitiz Equity Ventures (Philippines)

 

Pre-qualified Bidders

1. Team Polaris – Manila Water
Consortium Members: Manila Water; M.E. Sicat Construction; J.H. Patawaran Construction
Authorized Representative: Ms. Loida Dino
loida.dino@manilawater.com

2. First Philippine Holdings Corp. and Abeima Consortium
Consortium Members: First Philippines Holdings Corp.; Abeinsa Infraestructuras Medio Ambiente, S.A.
Authorized Representative: Mr. Ferdinand Edwin Coseteng
fscoseteng@firstgen.com.ph
edwin.coseteng@gmail.com

3. Filinvest Agua Consortium
Consortium Members: Filinvest Development Corporation; Tecnicas De Desalinizacion De Aguas, S.A.
Authorized Representative: Mr. Eleuterio D. Coronel
eleuterio.coronel@filinvestgroup.com

4. SMC – K Water Consortium
Consortium Members: San Miguel Holdings Corp.; Korea Water Resources Corporation
Authorized Representative: Mr. Edgar Dona

5. Prime Alloy Water Consortium
Consortium Members: Prime Water Infrastructure Corp.; MTD Capital BHD; Biwater International Ltd.
Authorized Representative: Me. Fe T. Rebancos

 

Bidders

1. Team Polaris – Manila Water
Consortium Members: Manila Water; M.E. Sicat Construction; J.H. Patawaran Construction
Authorized Representative: Ms. Loida Dino
loida.dino@manilawater.com

2. SMC – K Water Consortium
Consortium Members: San Miguel Holdings Corp.; Korea Water Resources Corporation
Authorized Representative: Mr. Edgar Dona

3. Prime Alloy Water Consortium
Consortium Members: Prime Water Infrastructure Corp.; MTD Capital BHD; Biwater International Ltd.
Authorized Representative: Me. Fe T. Rebancos

Winning Bidder/s

SMC – K Water Consortium
Consortium Members: San Miguel Holdings Corp. and  Korea Water Resources Corporation

  • ENGR. JOSE ALFREDO B. ESCOTO, JR.
    Project Manager, MWSS
    (+632) 8922-3757
  • ENGR. MIA IRISH M. ZOTOMAYOR
    Project Monitoring Officer, PPP Center
    (+632) 809.4146 local 5204