Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project

Project Brief

06Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
07Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
08Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
09Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
10Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
11Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
01Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
02Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
03Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
04Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
05Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
06Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
07Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
08Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
09Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
10Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
11Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
01Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
02Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
03Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
04Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
05Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg
06Daang Hari-SLEX Link Road (Muntinlupa-Cavite Expressway) Project (May 2017).jpg

Implementing Agency

Department of Public Works and Highways (DPWH)

Project Description

The Daang Hari – SLEX Link Road Project or what is now called the Muntinlupa-Cavite Expressway (MCX) is a new 4-kilometer 4-lane toll road, from the junction of Daang Reyna and Daang Hari in Las Piñas/Bacoor, Cavite to SLEX through the Susana Heights Interchange in Muntinlupa, traversing the New Bilibid Prison (NBP) Reservation. The link-road uses the Susana Heights Interchange as exit and entry from north and south of SLEX. The project included the construction of a new bridge/widening of the existing bridge crossing SLEX as well as the expansion of the Susana Heights toll plaza. Commercial operations commenced in July 2015.

Estimated Project Cost During Approval

PhP 2.23 Billion

Procurement Mode

Solicited

Contractual Scheme

Build-Transfer-and-Operate (BTO)

Contract Term

30 years

Implementation Mode

National

Region

  • NATIONAL CAPITAL REGION

Sector

Roads

Project Proponent

Ayala Corporation

Status

Operational since July 24, 2015

The 1st Toll Rate Adjustment approved by TRB has been implemented on May 20, 2019.

The provisional toll rate adjustment approved by TRB will be implemented on a staggered basis. The first tranche has been implemented on November 3, 2023. Second tranche is scheduled to be implemented on 2024.

Source: Toll Regulatory Board

List of Bidders

Prospective Bidders

1. J.D. Legaspi Const.
2. C.M. Pancho Const., Inc.
3. Marcbuilt Const., Inc.
4. Star Infrastructure Dev’t. Corp.
5. E.F.C. Ent.
6. M.T.D. Group
7. R-II Builders, Inc.
8. Ayala Corporation
9. Optimal Infrastructure Dev’t., Inc.
10. PT Citra Lamtoro Gung Persada
11. Monte Oro Resources and Energy, Inc.
12. IL and FS Transportation Network Ltd.
13. V.T. Lao Consortium
14. China International Water and Electric Corp.
15. Citra Metro Manila Tollways Corporation
16. Metro Pacific Tollways Corp.
17. BF Corporation
18. D.M. Consuji Inc.
19. D.M. Wenceslao & Associates, Inc/Kingsroad Consortium
20. Citimax Group Inc.
21. Megawide Construction Corporation
22. F.F. Cruz and Co., Inc.
23. EGIS Project Developer of Infrastructure and Services
24. State Properties Corporation
25. Korea Consultants International

Pre-qualified Bidders

1. Ayala Corporation
2. South Expresslink Corporation
3. Joint Venture of D.M. Consuji and C.M. Pancho

Bidders

1. Ayala Corporation
2. South Expresslink Corporation

Winning Bidder/s

Ayala Corporation

  • MS. MARIA CATALINA E. CABRAL
    Undersecretary, Department of Public Works and Highways (DPWH)
    (+632) 5304.3268
  • MS. WYNONA MARIE R. SILVERIO
    Project Monitoring Officer, PPP Center
    (+632) 8709.4146 local 5206