The auxiliary turbines 4 & 5 of the Angat Hydro-Electric Power Plant (AHEPP) are underperforming in its current state. Â The modernization of the auxiliary units is intended to generate the 28MW at full capacity and provide additional power capacity generation for the Luzon Grid. Â This project optimizes the use of an existing asset by allowing the private sector to rehabilitate and upgrade the auxiliary turbines, and efficiently operate and maintain said facility, while the government earns reasonable revenue.
Metro Manila Waterworks and Sewerage System (MWSS)
The project involves the rehabilitation, operation, and maintenance of the  MWSS-owned auxiliary turbines 4 and 5 installed in AHEPP Compound in San Lorenzo, Norzagaray, Bulacan.  Specifically, the private proponent shall :  a) renovate and modernize the existing 1 x 10 MW (Unit #4) and 1 x 18 MW (Unit #5) Auxilliary Turbines; b) construct a separate control room; c) construct a new switchyard and transformer area; and d) operate and maintain the modernized Auxilliary Turbines #4 and #5.
PHP 1.155 Billion | USD 27.5 Million
Rehabilitate-Operate-Maintain (ROM)
20 years inclusive of construction
Bidders due diligence ongoing.
♦ Aguirre Abano Panfilo Pares Pineda and Agustin Law Office
♦ DMCI Power Corp.
♦ EEI Corporation
♦ First Gen Energy Philippines
♦ Kaltimex Energy Philippines
♦ K-Water Resources Corporation
♦ Marubeni Corporation
♦ Meralco Power Generation
♦ SN Aboitiz Power
♦ Sta. Clara Power
♦ Sunway Waters and Electric Co.
♦ Trans-Asia Oil and Energy Development Corp.
MR. GERARDO ESQUIVEL
Administrator, MWSS
(+632) 922-3757
MR. JOJO DORADO
Project Manager, MWSS
(+632) 928-5691
MS. MA. CRISTINA CLEOFAS
Project Manager, PPP Center
(+632) 990-0721 loc. 6104
 *Approved PDMF Support